Sunday, July 25, 2010

Organisation


Organising Committee


The organisation was beset by delays: in January 2005, the Indian Olympic Association vice-chairman Raja Randhir Singh expressed concern that Delhi was not up to speed in forming and organising its games committee and, following a 2009 Indian Government report showing two thirds of venues were behind schedule, Commonwealth Games Federation president Mike Fennell stated that the slow progress of preparations represented a serious risk to the event. Singh called for a revamp of the games' organising committees:  Jarnail Singh, a former Secretary of the Government of India, was appointed as the Chief Executive Officer and Indian Olympic Association president Suresh Kalmadi was appointed as head of the committee. In spite of delays, commentators stated that they are confident that India will successfully host the games and do so on time.
At the launch of the Queen’s Baton Relay in October 2009, the Business Club of India (BCI) was formed through the partnership of the organising committee, the Confederation of Indian Industry (CII) and the Federation of Indian Chambers of Commerce and Industry (FICCI). The BCI was formed to both market the Games and promote Indian business interests internationally.

Costs


The total budget estimated for hosting the Games is US$ 1.6 billion and this amount excludes non-sports-related infrastructure development in the city like airports, roads and other structures. This will likely make the 2010 Commonwealth Games the most expensive Commonwealth Games ever, being larger than the previous games in Melbourne 2006 (approx. US$ 1.1 billion).


Source :- 

No comments:

Post a Comment